QAKFD
If Ground power is powering both Transfer Busses, the APU is available, and is selected to power Transfer Bus 1, which statement is correct?
Explanation
FCOM 6.20.3, AC Power
With the airplane on the ground and both generator control switches OFF, or with both engines shut down, selecting the GRD PWR switch ON connects external power to both transfer busses. Likewise, selecting either APU GEN switch ON connects APU power to both transfer busses. Whichever source is selected last powers both busses. It is not possible to power one transfer bus with external power and one transfer bus with APU power.