QEBDR
If operating on a single IDG and an overload is sensed, the electrical system will shed the galleys and main bus from Transfer Bus 1 and then Transfer Bus 2 before then shedding the IFE busses if an overload is still sensed.
Explanation
FCOM 6.20.4, Automatic Load Shedding (Engine Generators)
For single generator operation, the system is designed to shed electrical load incrementally based on actual load sensing. The galleys and main bus on transfer bus 2 are shed first; if an overload is still sensed, the galleys and main bus on transfer bus 1 are shed; if overload still exists, the IFE buses are shed.
The order is transfer bus 2 first, then transfer bus 1.