QPIVO
If an IDG fails and the APU is not available to power the related Transfer Bus, what occurs first if an electrical overload is sensed?
Explanation
FCOM 6.20.4, Automatic Load Shedding (Engine Generators)
For single generator operation, the system is designed to shed electrical load incrementally based on actual load sensing. The galleys and main bus on transfer bus 2 are shed first; if an overload is still sensed, the galleys and main bus on transfer bus 1 are shed; if overload still exists, the IFE buses are shed.